Re: Different Projects have totally different project settings
Re: Different Projects have totally different project settings
- Subject: Re: Different Projects have totally different project settings
- From: Mike Lazear <email@hidden>
- Date: Tue, 4 Jan 2005 13:43:00 -0800
I sent my last reply directly to Dave instead of the list. The answer
to my question about converting turns out to be simple.
"Project/Upgrade All Tragets in Project to Native".
I'm not sure how I never noticed that option before but I would guess
it was because I didn't know that my projects was already native so I
did look for such an option before now. Looks like I'll have to learn
a new format for settings. At first glance it doesn't seem like there
is a one to one mapping but I'll guess I just have to step thru all
options.
Thanks,
Mike
On Jan 4, 2005, at 1:35 PM, Mike Lazear wrote:
When I converted from Project Builder to XCode (back in version 1.0 of
XCode) it asked about upgrading to XCode and I said yes. From then on
I didn't realize I wasn't in "native" mode. How do I convert from
what I have to the native mode?
I guess the only reason I wouldn't want to move forward is at this
point I know where to find the options and on the new format I'm not
sure where to find the settings I use most.
Thanks for the reply,
Mike
On Jan 4, 2005, at 12:11 PM, Dave Camp wrote:
it sounds like your existing project has a target that has not been
upgraded to native. I don't know if there is any way to take a new
native target and move it back to the old style. Is there a reason
you don't want to upgrade the older target to the new native format?
Dave
On Jan 4, 2005, at 10:50 AM, Mike Lazear wrote:
I've been working on a Carbon app for quite some time. It
originally was imported into XCode from a Project Builder project.
When I select "Project/Edit Active Target 'App'" I get a project
settings window that on the left side has:
Summary
Settings
Info.plist Entries
Build Phases
with lots of sections within those choices. The actual settings are
made in a panel on the right side of the screen.
I've just created a new Carbon app using "File/New Project". I then
selected "Carbon Application" for my type of project. For this
project when I select "Project/Edit Active Target 'App2'" I get a
project settings window that looks absolutely nothing like the
first. It has 5 tabs across the top: General, Build, Rules,
Properties, Comments. All settings are made below in a table type
format.
How do I make this second project come up with a project settings
window similar to what I usually get. It took me a while to figure
out how to use the project settings window for the first format and
I'm totally lost on how to find the same settings on the new
project.
Thanks,
Mike
_______________________________________________
Do not post admin requests to the list. They will be ignored.
Xcode-users mailing list (email@hidden)
Help/Unsubscribe/Update your Subscription:
email@hidden
This email sent to email@hidden
---
There's an old proverb that says just about whatever you want it to.
_______________________________________________
Do not post admin requests to the list. They will be ignored.
Xcode-users mailing list (email@hidden)
Help/Unsubscribe/Update your Subscription:
This email sent to email@hidden